Demand supply scenario

  • The state whose installed capacity (13566 MW Including wind generation ) is 3rd highest in the country i.e Maharashtra 20868 MW & Tamil Nadu 14408 MW.
  • The demand projected by 2017 is 18478 MW for the proposed projects as on date.
  • It is estimated by 2017 , Gujarat has a capacity to generate 40,039 MW (double the projected demand) to meet the requirement of any additional projects due to the rapid industrialization.

Capacity Addition Planned Till 2012 (in MW)

Year State Central Private Total Cumm. Add.
Capacity as on 25th February , 2010 11711
2009-10 250 402 750 1402 13113
2010-11 1060 421 700 2181 15294
2011-12 860 383 2222 3465 18759
Total 2170 1206 3672 7048 25807